|
The Walla Walla County Conservation District is dedicated
to conservation and restoration of the natural resources of
Walla Walla County, facilitated by working on a voluntary
basis with landowners to identify opportunities and create
solutions, while consistently providing education, information,
and assistance whenever possible. |

Conservation District Fish Screen |
Screening of irrigation diversion intakes with NMFS approved
screens is required by RCW 77.55.040. It is also one of the
actions Walla Walla Basin stakeholders agreed to do under
the Early Actions Program, which was intended to delay regulatory
actions by National Marine Fisheries Service (NMFS) and United
States Fish and Wildlife Service (USFWS) until the
Habitat Conservation Plan is completed. The WWCCD fish screen
program is the centerpiece of the Cooperative Compliance Review
Program, which is a partnership between WDFW, WWCCD, WWCC
and other agencies intended to help local irrigators voluntarily
install fish screens and protect them from actions by regulatory
agencies. Under this program WDFW recruits and maintains the
master list of irrigators enrolled in the program and the WWCCD secures
and administers grant funding, screen assessment, design, and installation.
The WWCCD currently has grant funding for the program from
BPA, USFWS, and SRFB amounting to about $800,000 and is installing 10-15
fish screens per month.
- Accomplishment to Date -- 400 irrigators
are signed up for program, 350 have been assessed, 300 are installed
- Work Remaining -- an estimated 100-200
unscreened diversions remain
- Where Help is Needed -- Recruitment would
be aided by a WDFW PR program to inform irrigators of the
consequences of not having an approved screen on their diversion.
This is especially true for the urban irrigators where it is
believed most of the unscreened pumping stations and diversions remain.
Riparian buffer installation is not required by law however,
it is one of the primary actions required under the Early
Action Plan agreement with NMFS and USFWS. Primarily USDA
and the state under the Conservation Reserve Enhancement Program
(CREP), which is administered, by the state Conservation Commission
have provided funding for riparian buffer installation. Walla
Walla County has roughly 25% of the CREP for the entire state
of Washington. The CREP program is currently experiencing
a shortage of state funds that could jeopardize its effectiveness
in the future.
- Accomplishment to Date -- 2900 acres
and 150 miles of riparian buffer installed.
- Work Remaining -- It is estimated 2/3
of the buffer work has been completed on eligible Walla Walla County streams.
- Where Help is Needed --Ensure state
funding is adequate to partner with the CREP program.
Flow measuring devices are required by RCW 90.03.360. Flow
meters will allow DOE to monitor compliance with irrigation
water rights but, more importantly, they will allow the irrigator
to document water use thus protecting water rights from relinquishment.
We also believe water will be saved because flow meters will
allow the irrigator to voluntarily abide by their water right.
DOE and SRFB provide funding for the flow meter program. This
program is administered in tandem with the fish screen program
with assessment and design conducted by the WWCCD project staff.
Contracts
to install meters are awarded on a low bid basis.
- Accomplishment to Date -- 50 new irrigators
signed up for the program in addition to, 35 irrigators
assessed, 25 designed, and 160 installed.
- Work Remaining -- Estimate 500 to 600
diversions without meters.
- Where Help is needed -- Recruitment
would be aided by a WDOE PR program to inform irrigators
of the consequences of not having an approved flow-measuring
device.
We believe this program has enormous potential to significantly
increase flows in the Walla Walla Basin. As with the CREP
program, the Irrigation Efficiency Program is administered
through the Conservation Commission. WWCCD works in concert
with the WWCC, Irrigation Technology group to execute this
program. WWCCD acquires funds, subcontracts with the college
for technical assistance on assessments and designs and bids
out actual construction of the project. We have completed
construction of our 3rd irrigation efficiency project and
are currently assessing the possibility of a 4th project.
These projects have resulted in significant savings of
trustable water during the critical spring and fall fish passage months.
- Accomplishment to Date -- 50 irrigation
projects assessed, 3 projects completed, none under construction,
1 project under design. There are also two irrigation water
conveyance (piping) projects under design (Lowden 2 and
Touchet East/West Irrigation District).
- Work Remaining -- Estimate 10 additional
projects in biennium
- Where Help is needed -- Ensure integrity
of current arrangement between Conservation Commission and
DOE.
In-stream work has become very difficult because of environmental
compliance requirements which has forced WWCCD to focus our
efforts elsewhere. Shining examples of WWCCD’s achievements
are located throughout the county but Coppei Creek is the
example that WDFW and SRFB like to use as a showcase for the
basin.
- Accomplishment to Date -- 323 in-stream
structures installed
- Work Remaining -- Accurate estimates
are impossible at this time
- Where Help is needed -- Assistance from
WDFW and DOE on environmental compliance issues is critical.
Projects currently underway.
- Hofer Dam (Touchet River)
- Gose Street (Mill Creek)
The WWCCD shares office space with the USDA and works closely
with NRCS and FSA. The accomplishments of USDA often go unheralded.
In Walla Walla County we currently have 153,616 ac in USDA
programs (i.e. CRP) that convert marginal cropland to native
ground cover, with an additional ~23,000 acres of conservation
tillage under contract in the EQIP program.
|

Bull Trout |
- Specifications: Stationary screen.
Automated facility. Combined air/water pressurized
cleaning system. Capacity: 48 cfs.
- Location: The City’s intake
facility is in Oregon. The new screen replaced a traveling
screen originally installed in 1988 during replacement of its
14-mile transmission line between the Mill Creek Watershed
and the City.
- Chronology:
- In March 1999, the City met with USFW, Washington
Department of Fish and Wildlife, and Oregon Department
of Fish and Wildlife in response to concerns over
Bull Trout take.
- On July 28, 1999, the City in conjunction with
the agencies developed a schedule to bring City
facilities into compliance with new screening
standards.
- On October 8, 1999, the City completed improvements
on the existing screening facility as an interim
measure.
- In 2000, a joint design team panel was convened
with input from USFW, NOAA Fisheries, Washington
Department of Fish and Wildlife.
- Construction on the new screen commenced during
the summer of 2001 and was completed by September
26, 2001.
- Funding: The City partnered with
Bonneville Power Administration (BPA) and OR Department
of Fish and Wildlife to provide the necessary $425,000
in funding. The Confederated Tribes of the Umatilla
Indian Reservation (CTUIR) were instrumental in recommending
the project to the BPA.
- Fish Release: Subsequent to the
installation, the City assisted CTUIR in reintroducing
spring Chinook into Mill Creek.
|

New Fish Screen Platform |

City Intake with Fish Ladder |
|